Summer 2024 Paving Project
![](https://sharethehope.org/wp-content/uploads/2024/07/unnamed.png)
Magic Seal will start the first phase of the parking lot repair and resurfacing project on July 1st.
This involves removing the asphalt in the YELLOW section of the attached image and installing new stone and asphalt. This section is in the worst shape of the parking lot and requires the most work; therefore, it will be shut down while the work is done. The estimated schedule for this area is:
July 1-3: re-pave yellow
July 8-9: seal and stripe yellow
July 22 – seal and strip purple/green
July 23 – seal and strip blue
The funeral home has given permission for all EXITING traffic to use its lot during the first (yellow) phase of the parking lot work. Please pay attention to the signs posted during this project for daily instructions on where to go with your car and how to enter the building.
Thank you!
Building & Grounds Team
Hope Church